Costs allocated to tasks (not assigned to resources)has been through fixed
cost. I can print out a crosstab report showing actual cost but need to
print out remaining cost in a crosstab view. I am using project 2000.
 
S

Steve House [MVP]

Usage views are a form of crosstab. You can display the remaining cost in
the usage view, include other columns and set any filters you need, set the
timescale as desired and print the result.
 