Prioritization of projects for resource planning

M

Mickey

In Project Server 2007, is there any way to create a prioritization
between projects so one project will take resource priority over
another project? I have 53 projects which I need to import and they
will need to get worked on based upon mgmt's prioritization. I was
planning on resource leveling, but I'd like to level it so that it
takes into consideration mgmt's prioritization. Is this possible?


Thanks,
Mickey
 
D

Dale Howard [MVP]

Mickey --

In each project, you can set a Priority number between 0 and 1000, where
1000 is the highest priority possible. Click Project - Project Information
to set this value for each project. When leveling across multiple projects,
make sure you have each project open and make sure you set the Leveling
Order value to Priority Standard, which will make the Priority number the
first criteria in the leveling process. Hope this helps.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top