Using MS Project Standard 2007; Have two a set of tasks assigned to priority
900, other tasks assigned priority 500; I then level resources and expected
to see all resources assigned to Priority 900 tasks FIRST, then when all
Priority 900 tasks complete, THEN the priority 500 taskss BUT when I look at
my Gant I see Priority 500 interspersed (schedule-wise) with the Priority
900. Again I epxected all of my Priority 900 to have an end date in advance
of the Priority 500. What am I missing??