hi dear ;
i want to deffine tasks with more than 1000 priority score.
is there any way to trick msp ?
thank a lot
moradi
 
S

Steve House [MS Project MVP]

Why could you possibly need more than 1000 priority levels???? Priority can
be any value between 0 through 1000 with 1000 meaning "do not level." The
priority only affects resource leveling and is used to determine which tasks
out of a set of tasks are moved in the leveling process, lower priority
tasks being delayed before any higher priority tasks are affected. Since
1000 means don't move it under any circumstances, a value of more than 1000
would be meaningless.
 