S
smw
I need to have a separate line item in my plan for the lead-times on several
purchases. Example: order is placed on 6/30/2010, lead time to delivery is
60 calendar days, delivery would be on 8/28/2010. To do this I created a
lead-time calendar that makes every day a work day by setting all days to
8:00 AM - 5:00 PM. Task is fixed duration, 60d, non-estimated, calendar
LeadTime is assigned to the task, no resources specified.
The problem; project computes the Planned End Date at 8/22/2010 which by my
calculation is 7 days short of 60. Changing the calendar attached to this
task to the 24hour one increases the discrepancy.
Any suggestions will of course be greatly appreciated.
Steven Wheeler
purchases. Example: order is placed on 6/30/2010, lead time to delivery is
60 calendar days, delivery would be on 8/28/2010. To do this I created a
lead-time calendar that makes every day a work day by setting all days to
8:00 AM - 5:00 PM. Task is fixed duration, 60d, non-estimated, calendar
LeadTime is assigned to the task, no resources specified.
The problem; project computes the Planned End Date at 8/22/2010 which by my
calculation is 7 days short of 60. Changing the calendar attached to this
task to the 24hour one increases the discrepancy.
Any suggestions will of course be greatly appreciated.
Steven Wheeler