Barry
I have a fixed duration task with multiple resources assigned. Each resource
has been assigned some effort to be performed within a three week task. None
exceed more than 15 hours. One week in, I see that I need to plan more time
on the task than originally baselined for each of the resources. When I
increase their effort by approximately 5-10 hours, the end date is
automatically readjusted into 2005. Why does this happen? How can I stop
the date from readjusting.
Notes:
* we do not have the option for auto-leveling on
* we do not have the option for auto-add resources or task on either
* I did not re-baseline when adding the additional effort since it was not
part of my orginal estimate.
has been assigned some effort to be performed within a three week task. None
exceed more than 15 hours. One week in, I see that I need to plan more time
on the task than originally baselined for each of the resources. When I
increase their effort by approximately 5-10 hours, the end date is
automatically readjusted into 2005. Why does this happen? How can I stop
the date from readjusting.
Notes:
* we do not have the option for auto-leveling on
* we do not have the option for auto-add resources or task on either
* I did not re-baseline when adding the additional effort since it was not
part of my orginal estimate.