probability that project will we finished two days before planed dayin project

T

talar

Hello, I'm trying to find out where Microsoft Project 2007 shows
probability or variance for critical task.
For eg. I would like to know what is probability that project will be
finished on 15 december (planed date is 17 dec).
I have calculated PERT for every task but I can't even find variance
column to calulate it manually from equation:
z = (d-m)/sd
where:
d - specific date
m - mean date
sd - standard deviation
 
R

Rod Gill

Project Doesn't do that calc, but you can buy a Monte Carlo add-in that does
more. You also need a full Risks analysis with contingency calculated from
the risks.

--

Rod Gill
Microsoft MVP for Project

Author of the only book on Project VBA, see:
http://www.projectvbabook.com




talar said:
Hello, I'm trying to find out where Microsoft Project 2007 shows
probability or variance for critical task.
For eg. I would like to know what is probability that project will be
finished on 15 december (planed date is 17 dec).
I have calculated PERT for every task but I can't even find variance
column to calulate it manually from equation:
z = (d-m)/sd
where:
d - specific date
m - mean date
sd - standard deviation

__________ Information from ESET Smart Security, version of virus
signature database 4671 (20091208) __________

The message was checked by ESET Smart Security.

http://www.eset.com

__________ Information from ESET Smart Security, version of virus signature database 4671 (20091208) __________

The message was checked by ESET Smart Security.

http://www.eset.com
 
S

salgud

Hello, I'm trying to find out where Microsoft Project 2007 shows
probability or variance for critical task.
For eg. I would like to know what is probability that project will be
finished on 15 december (planed date is 17 dec).
I have calculated PERT for every task but I can't even find variance
column to calulate it manually from equation:
z = (d-m)/sd
where:
d - specific date
m - mean date
sd - standard deviation

Listen to Rod. Besides the fact that Risk Analysis software will do all
that and more for you, PERT has been found to be statistically unsound.
Yes, I know it's been in use for years. I first learned and applied it in
the 1970's, and it had been around for a while by then. Nonetheless, it's
not a valid method for getting representative risk-based estimates of task
durations. Monte Carlo analysis is.

Hope this helps.
 
T

talar

Listen to Rod. Besides the fact that Risk Analysis software will do all
that and more for you, PERT has been found to be statistically unsound.
Yes, I know it's been in use for years. I first learned and applied it in
the 1970's, and it had been around for a while by then. Nonetheless, it's
not a valid method for getting representative risk-based estimates of task
durations. Monte Carlo analysis is.

Hope this helps.

Thanks much for your answers, I will take a look at monte carlo
analysis. I found that there is a Microsoft Project 2007 VBA macro to
use Monte Carlo so I will take a closer look to it :)
 
M

Michael.Tarnowski

Thanks much for your answers, I will take a look at monte carlo
analysis. I found that there is a Microsoft Project 2007 VBA macro to
use Monte Carlo so I will take a closer look to it :)

Hi talar,
where did you find this monte-carlo VBA macro? - Does it apply to
previous MSP versions?
Cheers Michael
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top