B
basim alvi
Hi,
when project manager assign the task to team member which is 8 HOURS and it
is estimated .
but team member complete this task with in FIVE HOURS and (% WORK COMPLETE
Column ) in time sheet is showing 94% completed . and team member dont want
to enter 3 HOURS more because he has compeleted his task with in FIVE HOURS
.. and he want to spend other 3 hours to do another task . although in my
company we have set (8 hours daily).
Team members cant enter more than 8 hours .
Team member want that in time sheet it must Show 100 % completed.
what is the problem is this and how it can solve
Regards
Basim Alvi
when project manager assign the task to team member which is 8 HOURS and it
is estimated .
but team member complete this task with in FIVE HOURS and (% WORK COMPLETE
Column ) in time sheet is showing 94% completed . and team member dont want
to enter 3 HOURS more because he has compeleted his task with in FIVE HOURS
.. and he want to spend other 3 hours to do another task . although in my
company we have set (8 hours daily).
Team members cant enter more than 8 hours .
Team member want that in time sheet it must Show 100 % completed.
what is the problem is this and how it can solve
Regards
Basim Alvi