Problem calculating Finish Date

J

John T

When I enter an amount of work for a task, and assign a
resource, it calculates the duration and finish date
correctly, based on an 8 hour day. When I change the
Project working time to a 48 hour week and a 9.6 hour
day, Project recalcuates duration correctly, but does not
change the finish date. The finish date is always based
on an 8 hour day regardless of the number of hours per
day available. How can I get Project to recalculate the
finish date of a task based on a 9.6 hour day?

Thank you.

John
 
M

Mike Glen

Hi John,

Welcome to this Microsoft Project newsgroup :)

You might like to see FAQ Item: 5. Default Working Hours

FAQs, companion products and other useful Project information can be seen at
this web address: http://www.mvps.org/project/

Hope this helps - please let us know how you get on :)

Mike Glen
Project MVP
 