When I enter an amount of work for a task, and assign a
resource, it calculates the duration and finish date
correctly, based on an 8 hour day. When I change the
Project working time to a 48 hour week and a 9.6 hour
day, Project recalcuates duration correctly, but does not
change the finish date. The finish date is always based
on an 8 hour day regardless of the number of hours per
day available. How can I get Project to recalculate the
finish date of a task based on a 9.6 hour day?
Thank you.