Eric Johannsen
Hi,
I just started a brand new project file with Project Professional 2002.
I have a few grouped tasks like this:
My First Group (1 day)
Task A (3 days)
Task B (4 days)
My Second Group (1 day)
Task C (2 days)
Task D (3 days)
I would expect My First Group to calculate its duration as 4 days (since I
have not leveled resources yet), and My Second Group to calculate its
duration as 3 days (for the same reason).
Why is the duration staying at 1 day for the groups, and how can I fix that?
Thanks,
Eric
I just started a brand new project file with Project Professional 2002.
I have a few grouped tasks like this:
My First Group (1 day)
Task A (3 days)
Task B (4 days)
My Second Group (1 day)
Task C (2 days)
Task D (3 days)
I would expect My First Group to calculate its duration as 4 days (since I
have not leveled resources yet), and My Second Group to calculate its
duration as 3 days (for the same reason).
Why is the duration staying at 1 day for the groups, and how can I fix that?
Thanks,
Eric