Hi Folks,
I am trying to modify a resource calendar in 2007. I choose Tools, Change
Working Time, pick the resource's calendar and click Work Weeks, I select
Default and click Details. Then I select Monday through Friday under Select
days and choose Set day(s) to the specified working times. I change the
default 5:00 PM to 7:00 PM and click OK twice. When I return to the dialog
box later I discover the times have reverted back to 5:00PM.
Any assistance would be appreciated.
I am trying to modify a resource calendar in 2007. I choose Tools, Change
Working Time, pick the resource's calendar and click Work Weeks, I select
Default and click Details. Then I select Monday through Friday under Select
days and choose Set day(s) to the specified working times. I change the
default 5:00 PM to 7:00 PM and click OK twice. When I return to the dialog
box later I discover the times have reverted back to 5:00PM.