Andy Wiltz
There are a couple of resources that have not been submitting their time
through PWA, so the workplan manager enters time directly into the workplan.
It is 8 hours a day for 1 task, so it's pretty simple. The issue arises
when looking in the workplan, there is 8 hours of work assigned to the task
for each day, but when 8 is entered in for actual work, both automatically
change to a slightly smaller number (7.83, or 7.77 hours).
Even after simply typing 8 and clicking away, why would Project change this
to a smaller number? The task is fixed work and there arent any constraints
(As soon as possible). Does anyone have any experience with this issue?
through PWA, so the workplan manager enters time directly into the workplan.
It is 8 hours a day for 1 task, so it's pretty simple. The issue arises
when looking in the workplan, there is 8 hours of work assigned to the task
for each day, but when 8 is entered in for actual work, both automatically
change to a slightly smaller number (7.83, or 7.77 hours).
Even after simply typing 8 and clicking away, why would Project change this
to a smaller number? The task is fixed work and there arent any constraints
(As soon as possible). Does anyone have any experience with this issue?