E
Eddie K
I am creating a project org structure with different work package groups
doing differient pieces of work...
In some instances i have work package managers with subordinates that are
themselves managers in other project areas with that original manger being a
subordinate to them and this i think is causing confusion....
Each area has a work package number
So for example,
WP 01
Eddie Keating - Manager
Fred Perry - Subordinate
Lester Piggot - Subordinate
WP02
Fred Perry - Manager
Eddie Keating - Subordinate
Lester Piggot - Subordinate
Is there a way that Visio can use the work package number as a kind of
"Primary Key" that can be used to differentiate between the different work
package areas and so reflect the project reporting lines even though there
are apparant paradoxes?
doing differient pieces of work...
In some instances i have work package managers with subordinates that are
themselves managers in other project areas with that original manger being a
subordinate to them and this i think is causing confusion....
Each area has a work package number
So for example,
WP 01
Eddie Keating - Manager
Fred Perry - Subordinate
Lester Piggot - Subordinate
WP02
Fred Perry - Manager
Eddie Keating - Subordinate
Lester Piggot - Subordinate
Is there a way that Visio can use the work package number as a kind of
"Primary Key" that can be used to differentiate between the different work
package areas and so reflect the project reporting lines even though there
are apparant paradoxes?