G
Guest
Hi all togehter!
I want to export both TimeScaleDatas and information out of the
resources-Area from MS Project to Excel. Here I have some problems
realizing it.
i) First I want to set the TimeScaleUnit to a pre-defined value, e.g.
Months. I have found no expression which finally takes effect by
changing the interval on the right side. (This should also works as
stand-alone tool)
ii) Further I want to define which information is displayed as
TimeScaleData on the right side. Here I just want select e.g. the
"Cost"-Row. How do I change it if e.g. also "Work" etc. is active?
iii) If I copy a value out of the left sides' .Work-Resource-Area, the
comma (",") is not be pasted in the new document, so that for example
2,33 [Hours] moves to 233 [Hours]. Why?
iiii) Finally, after all settings are done I want to copy special
information from the TimeScaleData. BUT: I have not found any way to
get these values in a direct way as someting like
"ActiveProject.Resources(Row).TimeScaleValues(Column)" so that I use
copy & paste as a temporary solution*. Therefor I have to jump from the
left side over to the right one. "PaneNext" has no effect!! Therefor I
have up to present to ensure that the TimeScale-Field has the focus
when I run the macro. But my intention is, that the macro itsself
checks which element is focused and changed it automatically if needed.
It would be assist me greatly if somebody could help me!
Kind Regards!
Nachtigall
*Does anybody know such an expression?
I want to export both TimeScaleDatas and information out of the
resources-Area from MS Project to Excel. Here I have some problems
realizing it.
i) First I want to set the TimeScaleUnit to a pre-defined value, e.g.
Months. I have found no expression which finally takes effect by
changing the interval on the right side. (This should also works as
stand-alone tool)
ii) Further I want to define which information is displayed as
TimeScaleData on the right side. Here I just want select e.g. the
"Cost"-Row. How do I change it if e.g. also "Work" etc. is active?
iii) If I copy a value out of the left sides' .Work-Resource-Area, the
comma (",") is not be pasted in the new document, so that for example
2,33 [Hours] moves to 233 [Hours]. Why?
iiii) Finally, after all settings are done I want to copy special
information from the TimeScaleData. BUT: I have not found any way to
get these values in a direct way as someting like
"ActiveProject.Resources(Row).TimeScaleValues(Column)" so that I use
copy & paste as a temporary solution*. Therefor I have to jump from the
left side over to the right one. "PaneNext" has no effect!! Therefor I
have up to present to ensure that the TimeScale-Field has the focus
when I run the macro. But my intention is, that the macro itsself
checks which element is focused and changed it automatically if needed.
It would be assist me greatly if somebody could help me!
Kind Regards!
Nachtigall
*Does anybody know such an expression?