M
Mal Watts
All;
I have a problem when exporting data to Excel for analysis. Actually, two
problems. Would appreciate anyone's advice.
1. I'm exporting BCWP, BCWS, ACWP, SV and CV fields to Excel 2003,
from Project Standard 2002. I get no error messages, and I'm exporting
about
100 "time periods". After the 'status date' all of my exported fields are
filled
with zeros- even BCWS, which is my baseline data. How can I see the
complete "S-curve" of my baseline data over my entire project timeline ?
I can't see how it makes sense for MS Project to "hide" my baseline, even if
it
only reports data up to the "status date" for the other fields.
The "implied solution" is to set status date to end-of-project- but that's
not actually
what I want; I need to see how I'm going (up to status date = today), but
in the
context of the overall earned-value curve, over the entire project. I need
to be
able to report this to senior management in the form of a familiar
earned-value curve.
2. How do we overcome the only-255-columns-in-Excel problem ? I want to
analyze a project which has more than 255 time-periods. In this case,
duration longer than 255 days, and I want to analyze day-by-day. At
present, my workaround has been to analyze week-by-week, but that's more of
a hack than a solution.
Thanks for any help,
Mal.
I have a problem when exporting data to Excel for analysis. Actually, two
problems. Would appreciate anyone's advice.
1. I'm exporting BCWP, BCWS, ACWP, SV and CV fields to Excel 2003,
from Project Standard 2002. I get no error messages, and I'm exporting
about
100 "time periods". After the 'status date' all of my exported fields are
filled
with zeros- even BCWS, which is my baseline data. How can I see the
complete "S-curve" of my baseline data over my entire project timeline ?
I can't see how it makes sense for MS Project to "hide" my baseline, even if
it
only reports data up to the "status date" for the other fields.
The "implied solution" is to set status date to end-of-project- but that's
not actually
what I want; I need to see how I'm going (up to status date = today), but
in the
context of the overall earned-value curve, over the entire project. I need
to be
able to report this to senior management in the form of a familiar
earned-value curve.
2. How do we overcome the only-255-columns-in-Excel problem ? I want to
analyze a project which has more than 255 time-periods. In this case,
duration longer than 255 days, and I want to analyze day-by-day. At
present, my workaround has been to analyze week-by-week, but that's more of
a hack than a solution.
Thanks for any help,
Mal.