Jan M. said:
Hi John,
I have looked into the problem a little deeper:
I was using physical percent physical complete to calculate earned value:
using % complete instead solved the matching problem between the earned value
table and the time scale. But I still have the problem that made me choose
physical % complete instead of % complete:
I have applied work contours to some activities: mostly bells and late
peaks. So the work was planned to start very slowly. But we managed to put in
much more work than planned in the first activities. Unfortunately, the
earned value calculation with % complete was not showing reality: CPI was way
too low and FAC was saying my budget would almost doublec.
Personnally, I think that % work complete is more precise than % complete in
earned value calculation. Unfortunately, MS Project only allows % complete or
% physical complete in earned value calculations. So I decided to paste the
field % work complete in the field % physical complete and use % physical
complete to calculate earned value. CPI and SPI seemed much more realistic
this way. But I ended up with the problem we've been discussing for a couple
of days.
Have you ever heard of people having this discrepency problem between earned
value table and time scale using % physical complete.?
Since we are using Project Server, it is very easy to us to collect actual
work. So I want to use the proportionality rule for earned value calculation.
Any suggestions on how to use % work complete as a means of earned value
calculation?
Thanks
Jan,
To be honest, I have never used the % Physical Complete field. However a
little research into the on-line help file revealed the following
information (copied for reference only from the on-line MS Project Help):
"Remarks While the default earned value method field is % Complete,
you can change it to Physical % Complete for any tasks that apply.
You can also set the earned value method for a task on the Advanced tab
in the Task Information dialog box.
To set the default earned value method for all new tasks, click Options
on the Tools menu. Click the Calculation tab, and then click Earned
Value. You can also use this dialog box to choose which of the 11
available baselines should be used for earned value calculations.
The Physical % Complete field is available by default on the Tracking
table."
If you change the earned value method in your file, I'm betting it will
resolve the data discrepancy you are seeing.
You also mentioned you are using Project Server. Whether that also has
something to do with the problem I don't know. I have no experience with
Project Server but several of my fellow MVPs do. Hopefully one of them
will jump in and offer some advice.
Hope this helps.
John
Project MVP