Problem in viewing subproject tasks in PWA

J

jineshdalal

Hi

I'm facing the problem of not able to see subproject tasks along wit
master project tasks in PWA when I logon as a Project Admin. But i
I'll logon as a resource, the same can be viewed from the Resource
Task update page.

Do I need to make some settings to view it from Admin login?

Pl. suggest all possible solutions. Thanx
 
G

Gary L. Chefetz [MVP]

Where are you not seeing things that you expect to see? Please be specific.
Have you saved all of the subprojects to the server? What are you expecting?

Know this:

Each project must be saved to Project Server individually. In Project Web
Access views, you must open each project individually to see details.
Viewing a master project in PWA will display one summary line for each
inserted project. Does this help?
 