J
Jose
I din't found the exact solution to our problem.
People always put their time in PWA. This is correct. Real time here is ok.
The problem is that in real time in Project is wrong. There are few hours
than correct, few days and less time than the same day in PWA.
I tried the function Synchronize with Real Data but is doesn't work. I nedd
to "re-send" the data in PWA to Project. Is it possible?
Thanks.
People always put their time in PWA. This is correct. Real time here is ok.
The problem is that in real time in Project is wrong. There are few hours
than correct, few days and less time than the same day in PWA.
I tried the function Synchronize with Real Data but is doesn't work. I nedd
to "re-send" the data in PWA to Project. Is it possible?
Thanks.