A
aamadure
In my current project, I have entered all my Tasks, subtasks, and resourses.
Here is my problem
Some tasks are completed in 1 day (or 8h). These involve multiple subtasks
that use different resources. The total time for all subtasks totals 8h.
(ex. task--plant tours = 1d, subtasks--freezer, warehouse, processor,
packing =2h each)
PROBLEM: when i enter hours for subtasks the main task does not total
correctly, I get ### or other odd items.
Some tasks run 3-4 days, each subtask is equals 1 day. (ex. task--work with
drivers 3d, subtask--tom, dick, harry =1d each)
PROBLEM: when i enter days for each subtask the main task does not toal
correctly
1. How do I correctly enter hours for the subtasks so the main task totals
1d?
2. How do I enter days for subtasks so main tasks total the correct # of
days?
Here is my problem
Some tasks are completed in 1 day (or 8h). These involve multiple subtasks
that use different resources. The total time for all subtasks totals 8h.
(ex. task--plant tours = 1d, subtasks--freezer, warehouse, processor,
packing =2h each)
PROBLEM: when i enter hours for subtasks the main task does not total
correctly, I get ### or other odd items.
Some tasks run 3-4 days, each subtask is equals 1 day. (ex. task--work with
drivers 3d, subtask--tom, dick, harry =1d each)
PROBLEM: when i enter days for each subtask the main task does not toal
correctly
1. How do I correctly enter hours for the subtasks so the main task totals
1d?
2. How do I enter days for subtasks so main tasks total the correct # of
days?