J
Josh
Hi,
Here's the setup: I'm using MS Project 2003 connected to Project Server
2003, I have managed time periods turned on and I'm having everyone use PWA
to enter in their time against the project tasks.
Here's my problem: I'm getting project completed that have 0 remaining work
hours and the tasks aren't being set to complete. If I set the task manually
to complete, it give the message to sync with the project server and when I
do that, it re-set's the tasks back to incomplete. I'm stumped on this one
and really need to be able to get this one solved.
Any help would be appreciated.
Here's the setup: I'm using MS Project 2003 connected to Project Server
2003, I have managed time periods turned on and I'm having everyone use PWA
to enter in their time against the project tasks.
Here's my problem: I'm getting project completed that have 0 remaining work
hours and the tasks aren't being set to complete. If I set the task manually
to complete, it give the message to sync with the project server and when I
do that, it re-set's the tasks back to incomplete. I'm stumped on this one
and really need to be able to get this one solved.
Any help would be appreciated.