J
Jose Antonio
Hi,
We are using Project Server 2007 with all patches until october. We have a
problem with some tasks in Timesheets:
- This tasks have actual work typed by the user for certain days. Save. ok
- User go to My Tasks.
- Import timesheet. ok.
- Submit all. ok.
The actual work of some taks never appear in the project. Other tasks in the
same timesheet for the same project have actual work updated for the same
days.
I have seen this behaviour some times and now I would like to correct it for
ever. Deleting the timesheet and doing it again is not a good solution.
Any idea?
Regards
Jose
We are using Project Server 2007 with all patches until october. We have a
problem with some tasks in Timesheets:
- This tasks have actual work typed by the user for certain days. Save. ok
- User go to My Tasks.
- Import timesheet. ok.
- Submit all. ok.
The actual work of some taks never appear in the project. Other tasks in the
same timesheet for the same project have actual work updated for the same
days.
I have seen this behaviour some times and now I would like to correct it for
ever. Deleting the timesheet and doing it again is not a good solution.
Any idea?
Regards
Jose