Trevis
Can anyone explain why I am unable to use the Start1-10, Finish1-10 or the
Baseline1-10 fields in an Enerprise Code formula. I have tested using an
Enterprise Task Date field with simple formula = [Finish1] and returns an
error message "unrecognised field or function name" Has anyone else had the
same problem?