Hello Aelmalki,
Firstly, you're welcome and thanks for staying with this.
If I understand you correctly, you are attempting, in your example,
to import a task into a project with the following definition:
Project Start date: 01 Feb 2009
You are trying to import a task with a start date of 03 Jan 2009.
You are seeing a message from Project similar to:
"The start of Task X of "your file" is before the project starts.
Try one of the following:
- If you want the project to begin on this date, change the project
start date.
- If you entered a constraint that results in a task start date
earlier than the project start date, change either the constraints
or the project start date."
I just tried the process above on Project 2003. Despite the error
message, I was able to import tasks with start dates prior to the
start date of the Project. I don't know what you mean by
"truncates". Are you seeing the tasks not imported?
There isn't any way to make project ignore the start date of a
project. The start date of the project really should be the start
date of the earliest task. Is there a reason why you cannot set the
project start date to match the earliest date of any task?
Julie