P
Pat
We have a project that Custom Fields is set to "Hours of work done per
time period". This is only the 2nd week these resources have been
entering their own hours. Now we have a few resources entered
different actual hours for each day this week and the Project
Professional view is showing the same amount each day - like 1 hour -
each day for months into the future. Why is this occurring? They
haven't entered any actual hours past this week?
Pat Puckett
time period". This is only the 2nd week these resources have been
entering their own hours. Now we have a few resources entered
different actual hours for each day this week and the Project
Professional view is showing the same amount each day - like 1 hour -
each day for months into the future. Why is this occurring? They
haven't entered any actual hours past this week?
Pat Puckett