We are on Project Server 2003 and are trying to archive all our 2007 plans.
We are following the procedure where the resources are changed to proposed,
the tasks are republished then the project is put into an 'Archive' category
where no one has access.
Our problem is that when we do this many or our project managers are
receiving updates from as far back as January last year. We cannot figure
out why or how this is happening. Any ideas?