N
Néstor
I am trying to control a project with Earned Value, but I
have introduced all the data of the state of the project
and the BCWP is always 0 ?.
Can anybody help me, please?
have introduced all the data of the state of the project
and the BCWP is always 0 ?.
Can anybody help me, please?