Problem with BCWP

N

Néstor

I am trying to control a project with Earned Value, but I
have introduced all the data of the state of the project
and the BCWP is always 0 ?.
Can anybody help me, please?
 
G

Gérard Ducouret

Hello Néstor,
- Have you set the baseline : Tools / Tracking / Save baseline...
- Have you set the Status date : Project / Project Information / Status
date...

Gérard Ducouret [Project MVP]
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question