Hello,
Some projects are losing their values in the column bcwp and bcws.
I'm creating the project creating the tasks and saving the baseline, as
usually. But, some days, and maybe months later, when I reopened the project,
the bcwp and bcws values were set to 0 (zero).
The values for the baseline are still there in baseline column.
Is there a way to restore/recalculate these values in bcwp and bcws column?
Reset values (tools/tracking/set baseline - entire baseline) is not a option.
Any help will be appreciated.
Regards,
Caio
Some projects are losing their values in the column bcwp and bcws.
I'm creating the project creating the tasks and saving the baseline, as
usually. But, some days, and maybe months later, when I reopened the project,
the bcwp and bcws values were set to 0 (zero).
The values for the baseline are still there in baseline column.
Is there a way to restore/recalculate these values in bcwp and bcws column?
Reset values (tools/tracking/set baseline - entire baseline) is not a option.
Any help will be appreciated.
Regards,
Caio