problem with calanders - need help

J

j00cy

I am having one problem with one of my calanders for one of my
projects.

Start - 4/10/08
Finish - 5/10/08

There are two shifts,

19:00 4/10/08 to 05:00 5/10/08

05:00 - 23:00 5/10/08

I go into my calanders, i make a custom calander. How do i make this
information above in my calander so it shows what i have as my start /
finish times for both shifts. I have gone into the calander but it
says:

"the end of the shift must be greater than the start of the shift"

when i put in 19:00PM - 05:00AM.

What can i do to fix this problem up?

Thanks Peter
 
R

Rod Gill

Hi,

The problem is that any shift must start and finish on the same day. So your
shifts are:
00:00 to 5:00
05:00-23:00
23:00-23:59



--

Rod Gill
Microsoft MVP for Project

Author of the only book on Project VBA, see:
http://www.projectvbabook.com
 