New adopter of MS Project 07. I have a project whose saved baseline was
saved originally in MS Project 03. Now that I have MS Project 07, I am
needing to maintain the status of the project. As such I have a task that is
36edays long in duration that was 75% complete. Now its 95% complete and
when I change that % complete to reflect 95%, the edays go to 0edays and %
complete shows 95%. So then I try to reset the edays to 36edays, it won't
let me and looking at the task information I notice that all of a suddend
that task is now marked as a milestone. So I deselected the marked task as
milstone and back on the gnatt view I try again to enter 36edays. No dice,
it reverts back to "marked task as milstone".
This particular task is set to:
Constraint Type: As Soon As Possible
Task Type: Fixed Duration
And effort driven is unchecked.
Please advise on how I can adjust the %complete without affecting the edays.
saved originally in MS Project 03. Now that I have MS Project 07, I am
needing to maintain the status of the project. As such I have a task that is
36edays long in duration that was 75% complete. Now its 95% complete and
when I change that % complete to reflect 95%, the edays go to 0edays and %
complete shows 95%. So then I try to reset the edays to 36edays, it won't
let me and looking at the task information I notice that all of a suddend
that task is now marked as a milestone. So I deselected the marked task as
milstone and back on the gnatt view I try again to enter 36edays. No dice,
it reverts back to "marked task as milstone".
This particular task is set to:
Constraint Type: As Soon As Possible
Task Type: Fixed Duration
And effort driven is unchecked.
Please advise on how I can adjust the %complete without affecting the edays.