On a project plan we have used for some time we have a fixed duration task
which start date 26 Jan 2006, which has a duration of 32 days and Microsoft
Project calculates the Finish as 8 Mar 2006???? When it should be 32 days.
I have checked the calendar and the working days are only Monday to Friday
each week with no holidays. I have tried changing to fixed units and
deleting the duration start date etc. and then retyping but nothing seems to
help.
What else could be causing this miscalculation? How do I troubleshoot this
problem?
I have created another task, in the same project, with the same parameter
and the miscalculation happens. If however I open a new project and enter
the same parameters I get the correct end date of 10th March 2006. Please
help I am going this problem is driving me insane.
Thanks in advance
which start date 26 Jan 2006, which has a duration of 32 days and Microsoft
Project calculates the Finish as 8 Mar 2006???? When it should be 32 days.
I have checked the calendar and the working days are only Monday to Friday
each week with no holidays. I have tried changing to fixed units and
deleting the duration start date etc. and then retyping but nothing seems to
help.
What else could be causing this miscalculation? How do I troubleshoot this
problem?
I have created another task, in the same project, with the same parameter
and the miscalculation happens. If however I open a new project and enter
the same parameters I get the correct end date of 10th March 2006. Please
help I am going this problem is driving me insane.
Thanks in advance