Problem with Enterprise Custom field

J

JABAR

Hi All!
I have a problem with Enterprise Custom field. Namely, when I define field
in Project Server as: Entity – task, type – cost, Custom Attributes – None,
Calculation for aggregate rows – sum, I would like add this field to MS
Project, but when I add, values from this field on summary tasks display
“#ERRORâ€. I don’t know, what I’m doing wrong. Thank you for helps.
Regards,
Agnieszka
 
J

Jonathan Sofer [MVP]

Try hitting the F9 key to re-calculate the project. That will force all
custom formulas to re-calculate.
 
A

Agnieszka

Hello,

Thank you for answer. Unfortunately, F9 key has not helped.

Regards,
Agnieszka
 
J

Jonathan Sofer [MVP]

Strange because I tested this and also saw the error on summary rows but
when I hit F9, it calculated to 0.

What version are you on? 2007 SP1? Try maybe deleting your project cache
files:

1) Log out of Project Professional 2007
2) Go to Start > Run
3) Enter %appdata%
4) Navigate to \Microsoft\MS Project
5) Delete folder "12" and "Cache"
 
A

avivacarmen

Strange because I tested this and also saw the error on summary rows but
when I hit F9, it calculated to 0.

What version are you on?  2007 SP1?  Try maybe deleting your project cache
files:

1) Log out of Project Professional 2007
2) Go to Start > Run
3) Enter %appdata%
4) Navigate to \Microsoft\MS Project
5) Delete folder "12" and "Cache"

--
Jonathan Sofer [MVP]http://www.epmcentral.com







- Show quoted text -

Is your hourly rate for resources at least $1? (or 1 something) -
 

Ask a Question