D
DK
I run a standalone Integrated Master Schedule using MS Project Professional
2003, I don't use or have access to Project Server.
However, one of our sub-contractors uses Project Server and it seems that
ever since I cut and pasted some of their work packages into our IMS, we now
have custom enterprise fields (Text, Cost, Outline Codes, etc.) showing in
our schedule.
They don't appear in the Global.MPT, just the fields available to the
project schedule file. I can't seem to delete them using the rganizer and
when I try to customise an enterprise field they are greyed out.
I wouldn't normally bother, but every time I try and insert a new column I
have to scroll through 30 or so custom enterprise fields and it's getting a
bit annoying.
Many thanks in advance,
DK
2003, I don't use or have access to Project Server.
However, one of our sub-contractors uses Project Server and it seems that
ever since I cut and pasted some of their work packages into our IMS, we now
have custom enterprise fields (Text, Cost, Outline Codes, etc.) showing in
our schedule.
They don't appear in the Global.MPT, just the fields available to the
project schedule file. I can't seem to delete them using the rganizer and
when I try to customise an enterprise field they are greyed out.
I wouldn't normally bother, but every time I try and insert a new column I
have to scroll through 30 or so custom enterprise fields and it's getting a
bit annoying.
Many thanks in advance,
DK