B
benromero
I am working on an MS 2002 project file and it is killing me. I have
the following problem:
* I have a taks which has a predecessor, (so task 19 should start 'as
soon as possible' after the completion of task 18) but when I change
the predecessor task's duration, the successor task does not change.
Background to the problem:
All tasks have 'start as soon as possible' constraints
None of the project tasks (about 150 of them in total) have any
constraints (no calendar icon in the "information" column. However the
successor task is acting as if it had a 'must start on date' since its
start date does not change when I change the predecessor task.
At some point the file had automatic leveling, but I cleared all
leveling and turned leveling automatically to off.
If I remove resources from that task, the problem is still there. I can
only delete that task (successor) and re-enter it, then make it a
successor again, and then it works. What could cause this?
Since I do not have any constraint icons (nor do I know what is causing
this) I have no way of knowing if this is happening anywhere else in
the file, so I cannot trust any of it.....any ideas will be greatly
appreciated....I have spent hours on this thing and I am literally
pulling all my hair out.....Thanks in advance.
the following problem:
* I have a taks which has a predecessor, (so task 19 should start 'as
soon as possible' after the completion of task 18) but when I change
the predecessor task's duration, the successor task does not change.
Background to the problem:
All tasks have 'start as soon as possible' constraints
None of the project tasks (about 150 of them in total) have any
constraints (no calendar icon in the "information" column. However the
successor task is acting as if it had a 'must start on date' since its
start date does not change when I change the predecessor task.
At some point the file had automatic leveling, but I cleared all
leveling and turned leveling automatically to off.
If I remove resources from that task, the problem is still there. I can
only delete that task (successor) and re-enter it, then make it a
successor again, and then it works. What could cause this?
Since I do not have any constraint icons (nor do I know what is causing
this) I have no way of knowing if this is happening anywhere else in
the file, so I cannot trust any of it.....any ideas will be greatly
appreciated....I have spent hours on this thing and I am literally
pulling all my hair out.....Thanks in advance.