Problem with Project Server and MSP 2003

  • Thread starter Microsoft Communities
  • Start date
M

Microsoft Communities

Hi,

I use MSProject 2003 and Project Server, .
I have a problem:
- I planned a task must be done in 4 hour (input to Work column). I work
8hour/day, so the Duration column of this task is 0.5 days (Unit of the
resource is 100%) (Start from 08:00 to 12:00). Task is Effort Driven, Fixed
Work type.
- I set "Specify the default method for reporting progress on tasks":
"Hours of work done per day or per week: Resources report the hours worked
on each task during each time period" on project server. So project members
input actual work day by day in Project Web Access.
- If they finish this task in 3hour, they use Project Web Access to input 3
in timesheet and 0 in remaining work and send information to manager for
update.
- After project manager approved this task, the actual duration in this
task changed to 1 days (from 08:00 to 17:00). But I only work for 3 hours
(from 08:00 to 11:00), duration must be 3/8 days. So if this task is
predecessor of another task (Task B), task B cannot start on 11:01, task B
is schedule from 08:00 on next day.

How to resolve this problem.
Sorry for the bad English :)

Thanks
 