J
Johnathan
hi, I have few questions regarding MS Project using vb.net:
1. May I know how to get the resource units allocated to a task in vb.net?
2. If I change the Hours-per-day of a project in vb.net, although it
successfully change the hours per day but there is a need to adjust other
parameter in the project file right? What I get when i change the hours per
day is each taks duration was reduce but that doesn't looks like what it
gonna be in reality. Please advise me.
1. May I know how to get the resource units allocated to a task in vb.net?
2. If I change the Hours-per-day of a project in vb.net, although it
successfully change the hours per day but there is a need to adjust other
parameter in the project file right? What I get when i change the hours per
day is each taks duration was reduce but that doesn't looks like what it
gonna be in reality. Please advise me.