H
Haris
Hi,
I had deleted 3 projects of my organization from PWA using clean up project
server database feature and then I had the new project schedules for the same
projects republished on PWA. For this, after deleting the old schedules, PMs
created new schedules for each project by following one of the following
procedures:
1. The old schedule was saved offline as mpp, modifications were made to it
and then it was imported to project server using the Import Project to
Enterprise feature.
2. After deletion of old schedule from PWA, a new schedule was developed and
was published with a new name while conntected to the project server.
3. After deletion of old shedule, a new schedule was developed offline, and
then was imported to PWA by using the import project method and saved with a
different name.
After that, the PM did both "Publish All information" and "Republish
Assignments" with the Overwrite actuals submitted by resources option
checked. We're using managed time periods on PWA and this feature was
disabled while carrying out the republishing activity.
Now the new assignments are viewable in resource time sheets and resource
assignment views. But no information of the projects published so, can be
viewed in Project Center. Instead, the following message is displayed:
=========
There is no information to display in this view
Either the project manager has not published the project plan or there is no
information in the project plan to display.
=========
Whats causing this message? Did we missed out on any steps to be followed?
Please guide.
Regards,
Haris
I had deleted 3 projects of my organization from PWA using clean up project
server database feature and then I had the new project schedules for the same
projects republished on PWA. For this, after deleting the old schedules, PMs
created new schedules for each project by following one of the following
procedures:
1. The old schedule was saved offline as mpp, modifications were made to it
and then it was imported to project server using the Import Project to
Enterprise feature.
2. After deletion of old schedule from PWA, a new schedule was developed and
was published with a new name while conntected to the project server.
3. After deletion of old shedule, a new schedule was developed offline, and
then was imported to PWA by using the import project method and saved with a
different name.
After that, the PM did both "Publish All information" and "Republish
Assignments" with the Overwrite actuals submitted by resources option
checked. We're using managed time periods on PWA and this feature was
disabled while carrying out the republishing activity.
Now the new assignments are viewable in resource time sheets and resource
assignment views. But no information of the projects published so, can be
viewed in Project Center. Instead, the following message is displayed:
=========
There is no information to display in this view
Either the project manager has not published the project plan or there is no
information in the project plan to display.
=========
Whats causing this message? Did we missed out on any steps to be followed?
Please guide.
Regards,
Haris