I would greatly appreciate it if somebody could help me with the
following problem:
- Create a task "Task 01", assign "Resource 01" at 50%, set "Work" to
5 days (resulting in 10 day "Duration")
- Go to "Resource Usage" view and add "Actual Work" line
- Update "Actual Work" so that the first two days are spent 100% (1d)
on the task (instead of working planned 50%)
- Go back to Gantt view
- The resource has now changed to 100% (why?), "Work" is at 5 days
(ok), "Remaining Work" is at 3 days (ok), but the "Duration" is 8 days
(why?). If resource went to 100% (not sure why but it did) then the
duration should go to 5 days (2 completed days plus remaining 3 days
of work at 100%)
Even if I go and edit the resource to be at 50% again NOTHING changes.
Any thoughts?
Thanks,
Petar
following problem:
- Create a task "Task 01", assign "Resource 01" at 50%, set "Work" to
5 days (resulting in 10 day "Duration")
- Go to "Resource Usage" view and add "Actual Work" line
- Update "Actual Work" so that the first two days are spent 100% (1d)
on the task (instead of working planned 50%)
- Go back to Gantt view
- The resource has now changed to 100% (why?), "Work" is at 5 days
(ok), "Remaining Work" is at 3 days (ok), but the "Duration" is 8 days
(why?). If resource went to 100% (not sure why but it did) then the
duration should go to 5 days (2 completed days plus remaining 3 days
of work at 100%)
Even if I go and edit the resource to be at 50% again NOTHING changes.
Any thoughts?
Thanks,
Petar