E
Elle
Hi, hope you can help...
I need to add resources to the tasks
They are PMO, PM, PD, Dir etc. We don't have named resources yet.
I have 5 PMO, 3 PD, 2 Dir and 1 PM etc
The task is 17 days of work. 5 days for PM, 5 days for PD and 10 days for Dir
I tried entering: PM[100%];PD[300%];Dir[200%] representing how many of each
we have, but surely this assumes that everyone is working 100% for the time
on that task? which is not the case.
So...
I have another task which is 100 days of work. 5 for PM, 5 for PMO, 60 for
PD and 30 for Dir
I tried entering: PMO[5%];PM[5%];PD[60%];Dir[30%] and the duration came
out at nearly 2000 days!!!
AHHH how can I show this correctly?
I need to add resources to the tasks
They are PMO, PM, PD, Dir etc. We don't have named resources yet.
I have 5 PMO, 3 PD, 2 Dir and 1 PM etc
The task is 17 days of work. 5 days for PM, 5 days for PD and 10 days for Dir
I tried entering: PM[100%];PD[300%];Dir[200%] representing how many of each
we have, but surely this assumes that everyone is working 100% for the time
on that task? which is not the case.
So...
I have another task which is 100 days of work. 5 for PM, 5 for PMO, 60 for
PD and 30 for Dir
I tried entering: PMO[5%];PM[5%];PD[60%];Dir[30%] and the duration came
out at nearly 2000 days!!!
AHHH how can I show this correctly?