A
Andrzej Jaworek
[Project Server 2007, PWA]
Hi all,
I have a problem with some projects. Earlier there was no problem. Since
some time there is problem...
Problem is...
Any of my resources adds a new task using Task Center in PWA (for
example: Start date of the tasj: 21 March 2008, duration: 4 h) a sends
it for approval. Project manager aproves this task and pubishes project.
Then when I go to Resource center in PWA select a resource which added a
task click to view his/her availability and see on the chart that a task
allready added isn't on 21 March but it is moved a few days back !!
It happens in my other projects too but not always. There is no rule
Sometimes task on the availability chart are ok and sometimes there are
moved a few days back.
If somone had had the same problem please for help.
Andy
Hi all,
I have a problem with some projects. Earlier there was no problem. Since
some time there is problem...
Problem is...
Any of my resources adds a new task using Task Center in PWA (for
example: Start date of the tasj: 21 March 2008, duration: 4 h) a sends
it for approval. Project manager aproves this task and pubishes project.
Then when I go to Resource center in PWA select a resource which added a
task click to view his/her availability and see on the chart that a task
allready added isn't on 21 March but it is moved a few days back !!
It happens in my other projects too but not always. There is no rule
Sometimes task on the availability chart are ok and sometimes there are
moved a few days back.
If somone had had the same problem please for help.
Andy