Problem with the Actual Work from PWA

V

Victor

I've got some strange behaviors with the actual work inserted from pwa.
We work with Project 2007 Server Sp1.
We use tasks fixed work and often our planned tasks are split in many parts
during execution phase.
We have 2 king of behaviors
1- Some times the actual work in the Resource Usage View changes values and
some decimal appear (8.88 or 7.12).
2- Normally Saturday is NoWorking day but some times we work also on
Saturday.When we import the actual work from PWA on Monday (after a Week
with Saturday working day) Project inserts some Actual Work hours on Monday.
This is very strange because the Team Member have not yet to create the
TimeSheet for next week.

Thank you for your help!

Victor
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top