Charles L. Simpson
On all of my projects, the Finish Variance on PWA and in on the Project
Summary line in Pro are not in sync.
For instance, on this one project the Finish Variance in Project Pro
is -2.94d and on PWA it says that the Finish Variance is -2.35d.
Any ideas as to why these to are not in sync?
Thanks!
--
---------------------------------------------------------------