We have Project Server 2003 SP2a . Lately we encountered a problem
with assignments which their work contour is set to "contoured" and
not "flat". We don't know why those assignments are set to
"contoured", but we suspect that this issue is causing differences/
changes in actual work which have been reported in the PWA.
for example: a report in the PWA of 8h, 8h, 8h has been changed to
fractions of hours like 7.9, 8.1... which is different than the
original report. Sometimes even the total hours is not identical to
the original report.
Can anyone explain why this happens and how we can overcome this
problem?
Thanks a lot for your help.
Zach.
with assignments which their work contour is set to "contoured" and
not "flat". We don't know why those assignments are set to
"contoured", but we suspect that this issue is causing differences/
changes in actual work which have been reported in the PWA.
for example: a report in the PWA of 8h, 8h, 8h has been changed to
fractions of hours like 7.9, 8.1... which is different than the
original report. Sometimes even the total hours is not identical to
the original report.
Can anyone explain why this happens and how we can overcome this
problem?
Thanks a lot for your help.
Zach.