I
Ian Wolstenholme
Hello
I have followed the instructions for creating a new "Text" column and
entering in the Day(DateDiff("d",[Start],[Finish])+1) & " days" formula and
the formula was accepted - but the answers do not make sense - for
instance....
a.. Milestone activities "0 days" duration come out as "31 days" elapsed
duration..
b.. A Start (03 Jun05) and Finish(27 May09) comes out as "6 days" ?
Ideally, I would like the new field(column) to provide elapsed time in weeks
between Start and Finish , I would like the new field(column) to provide
elapsed time in weeks between Start and Finish.
I'd appreciate any advice/help.
Thanks
Ian
I have followed the instructions for creating a new "Text" column and
entering in the Day(DateDiff("d",[Start],[Finish])+1) & " days" formula and
the formula was accepted - but the answers do not make sense - for
instance....
a.. Milestone activities "0 days" duration come out as "31 days" elapsed
duration..
b.. A Start (03 Jun05) and Finish(27 May09) comes out as "6 days" ?
Ideally, I would like the new field(column) to provide elapsed time in weeks
between Start and Finish , I would like the new field(column) to provide
elapsed time in weeks between Start and Finish.
I'd appreciate any advice/help.
Thanks
Ian