today I deinstall the Microsoft Project 2003 and install Microsoft Project
2007.
Now I have a big Problem:
when I add to my project plan 3 tasks:
Task1, task2 and Task3, I can connect the three task BUT the task are not
move automatically to the end of the last task.
The work flow I make this:
add Task1 on the date: 01.11.2007 duration: 1day
add Task2 on the date: 01.11.2007 duration: 1day
add Task3 on the date: 01.11.2007 duration: 1day
Normally when I connected the three tasks in my project 2003 the tasks
change the start day...
In 2003 it would looks like:
Task1 begin at 01.11.2007 duration 1 day
Task2 begin at 02.11.2007 duration 1 day
Task3 begin at 03.11.2007 duration 1 day
This doesn't happen in 2007
all three tasks are on the same day (01.11.2007) after I connect it.
Is it a bug?
What can I do?
Regards,
today I deinstall the Microsoft Project 2003 and install Microsoft Project
2007.
Now I have a big Problem:
when I add to my project plan 3 tasks:
Task1, task2 and Task3, I can connect the three task BUT the task are not
move automatically to the end of the last task.
The work flow I make this:
add Task1 on the date: 01.11.2007 duration: 1day
add Task2 on the date: 01.11.2007 duration: 1day
add Task3 on the date: 01.11.2007 duration: 1day
Normally when I connected the three tasks in my project 2003 the tasks
change the start day...
In 2003 it would looks like:
Task1 begin at 01.11.2007 duration 1 day
Task2 begin at 02.11.2007 duration 1 day
Task3 begin at 03.11.2007 duration 1 day
This doesn't happen in 2007
all three tasks are on the same day (01.11.2007) after I connect it.
Is it a bug?
What can I do?
Regards,