W
Wantok
When importing a project from an MPX file created by another application, the Project Start Date is set equal to the earliest tasks start date. This is OK, but then each task is given the same start date, even though individual start dates are supplied via the MPX file.
Does anyone know of a way to prevent this from happening ie to allow the dates in the MPX file to be assigned to each task.
This used to be the case in MS-Project 98, but since Project 2000 the above seems to be the case.
Project appears to take the view that the imported tasks are "New" and therefore assigns a constraint of ASAP and Schedule From Start Date.
Any help would be appreciated.
Does anyone know of a way to prevent this from happening ie to allow the dates in the MPX file to be assigned to each task.
This used to be the case in MS-Project 98, but since Project 2000 the above seems to be the case.
Project appears to take the view that the imported tasks are "New" and therefore assigns a constraint of ASAP and Schedule From Start Date.
Any help would be appreciated.