Hello I'm a new user from MS Project and I hope someone can help me.
* The task will take 2 hours to complete and the person has 7 days in which
to complete it ( payment will be for 2hours and not the whole week )
* The following week the same person will get a new task which will take 3
hours and once again has 7 days in which to complete it ( again payment will
be only for 3 hours and not for the 7 days )
* That same person will have a second task in the same week which will take
6 hours to complete ( payments will be for 6 hours )
The days must not be altered in the project. In all my reports there are too
many hours calculated. For each week there are 40 hours, therefore
3X40=120hours, but for the tasks there are only 2+3+6=11hours and if
anything is altered it will alter the whole project. The days can be longer
or shorter. I need a timetable for every Task. These Timetable must not
modify the calculated days.
Franz
* The task will take 2 hours to complete and the person has 7 days in which
to complete it ( payment will be for 2hours and not the whole week )
* The following week the same person will get a new task which will take 3
hours and once again has 7 days in which to complete it ( again payment will
be only for 3 hours and not for the 7 days )
* That same person will have a second task in the same week which will take
6 hours to complete ( payments will be for 6 hours )
The days must not be altered in the project. In all my reports there are too
many hours calculated. For each week there are 40 hours, therefore
3X40=120hours, but for the tasks there are only 2+3+6=11hours and if
anything is altered it will alter the whole project. The days can be longer
or shorter. I need a timetable for every Task. These Timetable must not
modify the calculated days.