Problems update % of completed

M

Marcelo M

Please help, this is mi situation. The Resources go to the My Tasks page and
update the % of complete. for example in "Task 1" 35%.
Then they press "update" and Project Server send the update information to
the Projects owner who must approve this change.
After this de Project Owner Accept all the tasks changes but, it doesn't
update de Project page. For example
on the Task Page of the resource says "Task 1 35%", but in the project
page says "Task 1 0%"
I don't know what's wrong. If anybody can help me, i'll be thanked!!
Thanks
 
D

Darrell

Marcelo,

After the project schedule has been updated the plan must also be saved and
published to the project server in order to send the new status to the PWA
users.

Darrell
 
M

Marcelo M

Darrell, thanks for the answer. But i forgot to say in the previous post that
with the owner of the project users. I accept the changes and then published
to project server. The message i received from the server is that everything
its ok and the projects was saved with no problems and all that. but at that
moment i see the screen (grid or ms project proffessional) that is not
updated. So i don't know why this is happening. It was working well up to a
couple of weeks. Sorry about my english.
 