C
clibby11
I am trying to set up a column to show graphical
indicators of Red-Yellow-Green for projects but not sure
how to do that or have it trigger an indicator based on a
condition. Example: If a project is 40% complete or less I
would like it to say is red. Or another example, if the
actual date is later than the planned end date of the task
by 2 days show Red as the graphical indicator.
Help!!
Thanks
indicators of Red-Yellow-Green for projects but not sure
how to do that or have it trigger an indicator based on a
condition. Example: If a project is 40% complete or less I
would like it to say is red. Or another example, if the
actual date is later than the planned end date of the task
by 2 days show Red as the graphical indicator.
Help!!
Thanks