E
Em
Hello and Help!
I created 114 subtasks whose start and completion dates vary. When I change
the percent complete using the Entry form (Gantt Chart view) , the
calculations are correct. Currently, we have completed 19% or 22 out of 114.
However, if I change the Actual Start and Finish dates in the Tracking sheet
or on Tools--Project--Tracking menu, the percent complete begins to decrease
with each new date change. (I'm changing the values to 100%).
Some info about the plan:
(1) The project plan has a baseline
(2) I copied the tasks into Excel and then pasted them back into a new
project plan for a clean set of data and can reproduce the problem.
(3) There are no constraints or predecessors assigned to the tasks.
Any assistance anyone can provide would be greatly appreciated.
Ema
I created 114 subtasks whose start and completion dates vary. When I change
the percent complete using the Entry form (Gantt Chart view) , the
calculations are correct. Currently, we have completed 19% or 22 out of 114.
However, if I change the Actual Start and Finish dates in the Tracking sheet
or on Tools--Project--Tracking menu, the percent complete begins to decrease
with each new date change. (I'm changing the values to 100%).
Some info about the plan:
(1) The project plan has a baseline
(2) I copied the tasks into Excel and then pasted them back into a new
project plan for a clean set of data and can reproduce the problem.
(3) There are no constraints or predecessors assigned to the tasks.
Any assistance anyone can provide would be greatly appreciated.
Ema