M
mttakimbo
I am having some problems setting up my resource calendars for the
first time.
We have some resources that work a standard 8-hour 5-day week and some
that work a 10-hour 4-day week (monday-thursday). I have created
resource calendars to reflect each need. These resources will often
work on the same tasks on the same projects.
On the project level, the base calendar is standard 5-day and the
Hours Per Day is set to 8.
My problem is when I am creating tasks for the 10-hour worker.
If I have a task with a duration of one day and I assign my 10-hour
worker to use 100% of units that day, it schedules him for 8 hours.
If I have a a task with a duration of 5 days (M-F), Project schedules
him for 39 hours, 9 on Monday, 10 on Tues-Thurs. Remember, he is not
available on Friday.
If I have a task with a duration of 4 days (M-Th), Project schedules
him for 38 hours, 10 on Mon-Wed, 8 on Thursday.
Why is this happening? Any help will be greatly appreciated.
Thanks,
Brian
first time.
We have some resources that work a standard 8-hour 5-day week and some
that work a 10-hour 4-day week (monday-thursday). I have created
resource calendars to reflect each need. These resources will often
work on the same tasks on the same projects.
On the project level, the base calendar is standard 5-day and the
Hours Per Day is set to 8.
My problem is when I am creating tasks for the 10-hour worker.
If I have a task with a duration of one day and I assign my 10-hour
worker to use 100% of units that day, it schedules him for 8 hours.
If I have a a task with a duration of 5 days (M-F), Project schedules
him for 39 hours, 9 on Monday, 10 on Tues-Thurs. Remember, he is not
available on Friday.
If I have a task with a duration of 4 days (M-Th), Project schedules
him for 38 hours, 10 on Mon-Wed, 8 on Thursday.
Why is this happening? Any help will be greatly appreciated.
Thanks,
Brian